VTP Withdraws. Two Hearings Remain. Wednesday, 6 pm.

Virginia Technology Park withdrew, which is a major win, but two important hearings remain: Winchester Gateway and Gibson Property. We have a chance to stop them and it is crucial for everyone to attend. Be there and make your voice heard. This newsletter is here to provide you with the facts to fight.

Public Hearing Wed. Oct 28
6:00 pm
Board of Supervisors
107 N Kent St
Critical Winchester Gateway CUP #03-26 Back Creek, Kernstown
Critical Gibson REZ #08-26 Opequon
Withdrawn VTP REZ #04-26 Stonewall, Clear Brook
Public Hearing 1 of 2 · Back Creek District

Winchester Gateway CUP #03-26

A 158-megawatt data center across the road from the Kernstown Battlefield. The HRAB and the Planning Commission said no. The draft ordinance is written as an approval.

The Board hears it only because the Sept 23 grandfathering resolution preserved the old ordinance for this application. Staff says megawatts were never disclosed; the applicant’s site assessment states 158 MW. The applicant’s noise addendum predicts 66–70 dB(A) daytime at two property lines, against a 65 dB(A) condition.

Read the special report
Public Hearing 2 of 2 · Opequon District

Gibson REZ #08-26

The Planning Commission said no, 11-2. The proffers are now on their fifth version.

The fast schedule is tied to a $10.96 million state grant whose application describes a 300-acre project, not the 244 acres being rezoned. Frederick Water’s emails, released under FOIA, say “right out of the gate the project will use more sewer than is available.”

Read the special report
Support This Work

Keeping You In The Know

Every fact in this issue came from a staff report or a FOIA request. Your contribution keeps it coming.

Donate

Protect Frederick is a 501(c)(4) organization. Contributions are not tax deductible.